F-35 Is The Biggest Money Sinkhole Ever
A new Government Accountability Office (GAO) report has found that Lockheed Martin and Pratt & Whitney, the primary contractors working on the F-35, made product deliveries 238 days late on average in 2024 — despite the program paying them hundreds of millions in performance incentive fees, which encourage completing tasks on-time